Home | Legislators | Committees | Media Center | Calendars | Kids | Resources | Contact Us

COMMITTEE ON PUBLIC WORKS

MINUTES: MAY 4, 2004 AT 9:30 AM

COMMITTEE ON PUBLIC WORKS MEMBERS PRESENT: Chairman Young; Legislators Oros, Rogowsky; STAFF PRESENT: Neglia, Perez-Sotillo

IN ATTENDANCE: Comm. Butler (DPW); A. Neuman (C.E.’S OFFICE)

ON THE MOTION OF LEGISLATOR OROS, SECONDED BY LEGISLATOR YOUNG, THE MINUTES WERE APPROVED ON JUNE 15, 2004. ALL IN FAVOR – AYE – 3-0.

MINUTES:

Meeting called to order by Chairman Young at 9:31 am.

Bond Acts Discussed:

B0009 – Bond Act authorizing the issuance of $200,000 in bonds- replacement of sanitary and storm piping, Valhalla campus. (03/22/04 -also referred to B&A) {Signed out by B&A on 05/03/04}

Comm. Butler (DPW) stated that the $200,000 request is to do an investigation and then follow up with the design on the sanitary and storm piping at the Valhalla campus.

Currently, there is over 40,000 linear feet of storm and sanitary line at the campus. There have been a number of problems over the last few years of roughly 10,000 linear ft. of piping.

They want to focus on this area first and then look at the rest of the piping.

It is similar to the program the county accomplished under the I/I (infiltration/inflow) program a couple of years ago.

Legislator Rogowsky suggested that DPW share with this committee a “global” report on what is going on all projects in the county.

Comm. Butler stated that close to $100,000 has been spent over the last 2-3 years to repair the sanitary and storm piping.

Motion by Leg. Rogowsky; Second by Leg. Oros. All in favor – aye – carried 3-0.

B0019 – Amended Bond act authorizing the issuance of $1,100,000 in bonds – repair utility tunnels, Valhalla campus. (03/22/04 – also referred to B&A) {Signed out by B&A on 05/03/04}

Comm. Butler (DPW) stated there are structural failures in the concrete in the tunnel system at the central heating plant in the Valhalla campus. This project will repair the structural integrity in those tunnel systems.

Motion by Leg. Oros; Second by Leg. Rogowsky. All in favor – aye – carried 3-0.

B0077 – Bond Act authorizing the issuance of $300,000 in bonds – infrastructure improvements, Valhalla campus. (03/22/04 – also referred to B&A) {Signed out by B&A on 05/03/04}

Comm. Butler (DPW) stated that this is actually a 5 year program that will handle infrastructure improvements at the Valhalla campus as well as the district office buildings. This project will remove all of the thousands of mercury devices in all the mechanical rooms at the central heating plant. They will be replaced with a state-of-the -art digital control system.

Motion by leg. Rogowsky; Second by Leg. Oros. All in favor – Aye – carried 3-0.

Chairman Young made a motion to adjourn at 9:51 am; Moved by Leg. Rogowsky. All those in Favor – Aye – 3-0.

Text:  Print: