Site Search
Capital Projects Dashboard
This interactive tool allows users to track the progress of all open capital projects approved by the Board of Legislators. These projects are in varying stages of completion. Some are “in progress,” while others are “delayed” or the legislators have not been furnished with information about their progress; others have simply been stopped by the Astorino Administration.
Each project displays its status, legislative information, the date passed, a description, the amount requested for each bond and which department is in charge of the work. This page will be updated regularly to reflect changes in the progress of each project.
369 open projects totaling $1,160,872,342 and
providing an estimated 12,003 jobs
|
|
|
|
*Click on an ACT # for more detail.
NOTE: Acts prior to 2008 are not available online. Please contact the Clerk's Office for copy of legislation.
AIRPORT - 4 Projects - $9,138,000
Status Act # Date Passed Capital Project # Description Bonds Requested 
2013-72 5/6/2013 A083A Terminal Systems Upgrade $5,288,000 
2013-71 5/6/2013 A0097 Domestic Water System Improvements $2,500,000 
2010-49 5/10/2010 A054A Rehabilitation of Various Taxiways-Section of Taxiway L $300,000 
2010-37 4/26/2010 A0086 Sewer Line Replacement Program $1,050,000 BUILDINGS, LAND & MISC - 29 Projects - $75,033,000
Status Act # Date Passed Capital Project # Description Bonds Requested 
2013-48 2013-04-15 BPF32 Infrastrucuture Repairs-Parking Structure, White Plains Complex $2,000,000 
2009-128 2009-08-10 B0081 Rehabilitation of Record Center, 2199 Saw Mill River Road, Elmsford $8,875,000 
2008-130 2008-07-08 BEL03 Renovations of 450 Saw Mill River Rd, Ardsley $7,000,000 
2007-83 2007-04-23 B0090 Retrofit Diesel Powered Vehicles $2,500,000 
2008-199 2008-11-10 B0075 Fire Alarm System Upgrade, MOB, WP $2,200,000 
2006-246A 2006-12-11 B0090 Retrofit Diesel Powered Vehicles $2,000,000 
2008-167 2008-09-08 B0097 Flood Mitigation, Various Locations $2,000,000 
2008-98 2008-07-08 B042A Roof Replacement Program (2007-2011), Various Locations- 85 Court St.. Mt Vernon Do, Mt. Kisco $1,555,000 
2002-72 2002 B0011 Replacement of Gas Mains, Valhalla Campus $1,200,000 
2008-90 2008-06-16 B0072 Rehabilitation of Passenger Elevators 112 East Post Rd, WP $1,200,000 
2006-246B 2006-12-11 B0090 Retrofit Diesel Powered Vehicles $1,000,000 
2007-234 2007-11-26 B0034 White Plains Complex, HVAC Equipment Reinforcement $ 995,000 
2012-112 2012-09-10 B035B Heavy Equipment Replacement Program (2006-2010) $ 500,000 
2012-113 2012-09-10 B035C Heavy Equipment Replacement Program (2012-2016) $ 350,000 
2011-95 2011-07-11 B0101 Cooling Tower Replacement, New Jail, Valhalla Campus $2,750,000 
2009-125 2009-08-10 B0071 Modification to Building Management System $7,400,000 
2010-119 2010-09-20 B042A Roof Replacement - Various 2007-2011-Valhalla Campus And Jail Annex $3,100,000 
2012-20 2012-03-26 B014C Exterior Infra Repairs White Plains Complex $2,200,000 
2010-75 2010-07-12 B0045 Putnam Right-of-Way South County Trailway $2,650,000 
2010-105 2010-09-07 B015B Interior Repairs- White Plains Complex $ 775,000 
2011-73 2011-05-23 B014B Infrastructure Repairs, White Plains Complex 2006-2010 $ 750,000 
2009-156 2009-10-05 B0083 Salt Storage Shed, Lake St Rd Maintenance Facility $ 675,000 
2012-58 2012-06-04 B0086 Equipment and Control Systems Upgrades, Central Heating Plant Valhalla $ 330,000 
2009-90 2009-05-26 B015B Interior Repairs- White Plains Complex $ 150,000 
2010-132 2010-10-04 BPF03 Parking Lots and Control Devices $ 148,000 
2008-135 2008-08-11 B0077 Infrastructure Improvements Valhalla Capmus Dob's (2004-2008)-Mt Kisko Elevators and Site Improvements
$1,080,000 
2011 BOL ADD 2011 NEW Saw Mill Day Lighting-River Park $9,000,000 
2011 BOL ADD 2011 NEW Saw Mill Day Lighting Parking-Parking Lot to Support Public Space from Saw Mill Daylight $6,800,000 
2011 BOL ADD 2011 B019A Repairs-Utility Tunnel Valhalla-Design,Construction & Repairs $3,850,000 CORRECTION - 11 Projects - $23,852,000
Status Act # Date Passed Capital Project # Description Bonds Requested 
2013-05-20 BCR50 Infirmary/Suicide Prevention $600,000 
2011-03-11 BCR5B Infrastructure Improvements (2006-2010)-Video Visitation $302,000 
2013-40 2011-03-11 BCR24 County Jail Renovations-Video Visitation $150,000 
2013-37 2011-03-11 BCR5B Infrastructure Improvements (2006-2010)-Elvevator, Fencing, Lighting $750,000 
2009-117 2009-06-22 BCR47 Security System Integration Project-Jail Division $8,340,000 
2007-148 2007-07-09 BCR24 County Jail Renovations $6,230,000 
2007-140 2007-07-09 BCR19 Life Safety Renovations $2,200,000 
2007-142 2007-07-09 BCR5B Infrastructure Improvements (2006-2010) $1,500,000 
2009-111 2009-06-22 BCR5B Infrastructure Improvements (2006-2010) $1,500,000 
2008-203 2008-11-01 BCR5B Infrastructure Improvements (2006-2010) $750,000 
2013-11 2013-01-28 BCR49 Jail Road System $1,530,000 COUNTY CLERK - 3 Projects - $2,425,000
EMERGENCY SERVICES - 4 Projects - $8,125,000
Status Act # Date Passed Capital Project # Description Bonds Requested 
2013-65 5/6/2013 BES12 County Public Access Defibrillation Equipment
$260,000 
2013-4 1/7/2013 BES05 DES Main Facility Rehab $1,590,000 
2007-91 5/7/2007 BFT05 Fire Training Center - Strip Mall Live Building $600,000 
2006-172 9/11/2006 BES03 Support Services Facility $5,675,000 INFORMATION TECHNOLOGY - 29 Projects - $22,851,000
Status Act # Date Passed Capital Project # Description Bonds Requested 
2013-60 5/6/2013 BIT6B Purchase of Computer Equipment 2011-2015 (Servers, Storage, Applications) $500,000 
2013-61 5/6/2013 BIT3B Desktop Systems 2012-2016 $980,000 
2013-62 5/6/2013 BIT4B Employee Productivity Systems 2013-2017 (Reusable Software Components) $1,000,000 
2013-63 5/6/2013 BIT7A Global Positioning Systems Phase II (GPS/AVL) $150,000 
2013-64 5/6/2013 BIT17 Network Infrastructure Upgrade $500,000 
2013-16 1/28/2013 BIT6B Purchase of Computer Equipment '11-'15 $500,000 
2013-10 1/28/2013 BIT15 Replacement of E911 Equipment $100,000 
2011-98 7/11/2011 BIT26 County-Wide Base Map Update $550,000 
2010-83 7/12/2010 BIT8A Financial Systems Review $2,000,000 
2010-95 8/9/2010 BIT17 Network Infrastructure Upgrade $500,000 
2009-197 11/23/2009 BIT4A Employee Productivity Systems (2008-2012) $1,250,000 
2009-180 11/9/2009 BIT4A Employee Productivity Systems (2008-2012) $1,000,000 
2009-145 9/21/2009 BIT09 Geographic Information Systems $725,000 
2009-121 7/7/2009 BIT15 Replacement of E-911 Equipment $1,050,000 
2009-80 5/11/2009 BIT6A Purchase of Computers (2007-2011) $500,000 
2009-83 5/11/2009 BIT22 Electronic Record Management System $250,000 
2009-84 5/11/2009 BIT3A New Desktop Systems (2007-2011) $960,000 
2012-160 11/13/2012 BIT4A Employee Productivity System 2008-2012 (District Attorneys Office, Other) $660,000 
2012-137 10/15/2012 BIT27 Upgrade of Jail Management System $700,000 
2012-148 10/15/2012 BIT3B Desktop Systems 2012-2016 (District Attorneys Office) $100,000 
2012-114 9/10/2012 BIT28 Replacement of Probation's Criminal Court Offender System $961,000 
2012-31 4/16/2012 BIT17 Network infrastructure upgrade $1,246,000 
2012-30 4/16/2012 BIT6B Purchase of Computer Equipment (2011-2015) $909,000 
2012-29 4/16/2012 BIT3A Desktop systems 2007-2011 $1,200,000 
2011 BOL ADD BGS26 Workforce Automation-Create a T&M Estimator and Billing System so a Blended Rate $250,000 
2011 BOL ADD BIT6A Purchase of Computer Equip-Servers $150,000 
2011 BOL ADD BIT09 Geographic Information-Perform the data entry of the standardized photographic element into local municipalities assessment systems. $3,000,000 
2008-162 9/8/2008 BIT09 Geographic Information Systems $400,000 
2007-185 9/24/2007 BIT18 Electronic Health Records System - Doc $760,000 LABS & RESEARCH - 7 Projects - $5,544,000
Status Act # Date Passed Capital Project # Description Bonds Requested 
2013-59 5/6/2013 BLR2C Labs and Research Equipment Acquisition (2011-2015)
$377,000 
2012-38 04/30/2012 BLR2C Labs and Research Equipment Acquisition (2011-2015) $450,000 
2011-162 10/17/2011 BLR2C Labs and Research Equipment Acquisition (2011-2015) $242,000 
2011-163 10/17/2011 BLR2B Labs and Research Equipment Acquisition (2006-2010) $450,000 
2010-117 09/20/2010
BLR2BLabs and Research Equipment Acquisition (2006-2010)
$505,000
2009-203 12/07/2009 BLR2B Labs and Research Equipment Acquisition (2006-2010) $3,270,000 
2009-182 11/09/2009 BLR07 HVAC Equipment Upgrade $250,000 LAW - 1 Project - $1,500,000
Status Act # Date Passed Capital Project # Description Bonds Requested 
2011 BOL ADD New Family Court-Restructuring of mandated family court facilities in various locations in Westchester County $1,500,000 PLANNING/PROPERTY ACQUISITION - 62 Projects - $113,945,380
Status Act # Date Passed Capital Project # Description Bonds Requested 
2013-94 5/20/2013 BPL50 Fair and Affordable Housing - Route 6 and Clayton Blvd (Construction) $1,900,000 
2013-93 5/20/2013 BPL50 Fair and Affordable Housing - Route 6 and Clayton Blvd (Acquisition)
$2,900,000 
2013-77 5/6/2013 BPL10 Land Acquisition-150 Lake Street White Plains
$1,140,000 
2013-36 2/25/2013 BPL23 Storm Water Management - Greenburgh (Fisher Lane) $800,000 
2009-79 4/27/2009 BPL26 Flood Mitigation/Mamaroneck Sheldrake River Basin $900,000 
2009-119 6/22/2009 SL102 Environmental Benefits Projects $780,000 
2009-213 12/7/2009 BPL21 Water Quality Improvement Projects (Manursing Island) $500,000 
2010-87 7/12/2010 BPL21 Water Quality Improvement-East Bank BRP $350,000 
2010-113 9/7/2010 BLA01 JFK Marina Trevor Park $1,000,000 
2010-160 11/29/2010 BPL01 State St. Academy Pl-Ossining $552,000 
2011-164 10/17/2011 BPL12 Tarrytown-Kensico Trailway $250,000 
2008 BOL ADD BLA01 Legacy Program $300,000 
2009-140 9/8/2009 BPL26 Flood Mitigation/ Rye, Rye Brook, Scarsdale & Tarrytown $4,500,000 
2009-221 12/7/2009 BPL10 60 West 1st St-Mt. Vernon $1,265,000 
2009-222 12/7/2009 BPL01 60 West 1st St-Mt. Vernon $1,552,000 
2009-232 12/21/2009 BLA01 Flowers Pk-New Rochelle $9,800,000 
2009-60 4/13/2009 BPL01 Fairview Housing Development-Greenburgh $2,070,000 
2010-158 11/29/2010 BPL10 Land Purchase State St-Academy $1,340,000 
2011-160 10/3/2011 BPL50 3372 Old Crompond Rd $2,930,000 
2011-80 6/6/2011 BPL01 Heritage Homes -New Rochelle $1,190,000 
2012-15 3/12/2012 BPL50 Fair and affordable housing (FAH) 445 north state rd briarcliff $1,510,000 
2011-17 1/31/2011 BPL10 Palmer Ave $320,000 
2012-152 10/15/2012 BPL10 New Homes Land- 867 Saw Mill Rvier Rd, Ardsley-Water Wheel Partners $935,000 
2012-151 10/15/2012 BPL50 Fair and Affordable Housing-867 Saw Mill Rvier Rd, Ardsley-Water Wheel Partners $735,000 
2012-146 10/15/2012 BPL50 Fair and Affordable Housing-525 Ellendale Ave, Rye Brook $200,000 
2012 BOL ADD BPL23 Stormwater Management Various County Facilities $400,000 
2011 BOL ADD NEW Storm Water Collection-County-wide sewer district Storm water collection system/downtown government center Getty square $9,900,000 
2012-106 9/24/2012 BPL01 Warburton Riverview Apartments $2,750,000 
2012-136 9/24/2012 BPL50 Fair and Affordable Housing-256-258 June Road, North Salem $4,000,000 
2011-66 5/23/2011 BPL01 Laporte $784,000 
2011 BOL ADD BPL01 3334 Crompond Rd. ,Yorktown 
2011 BOL ADD BPL01 33 Oak, 90 &100 Manhattan Ave. Fairview 
2011 BOL ADD BPL01 Academy Place, Ossining 
2011 BOL ADD BPL01 La Porte, 203 Gramatan Ave.,Mt.Vernon 
2011 BOL ADD BPL01 75 Stratton St. South,Yonkers 
2011 BOL ADD BPL01 50 Warburton Ave.,Yonkers 
2011 BOL ADD BPL01 303-307 S.Broadway,Yonkers 
2011 BOL ADD BPL01 500 Main St.,New Rochelle 
2011 BOL ADD BPL10 Grace Terrace Development,Mt.Vernon 
2011 BOL ADD BPL10 37 Wildwood Rd.,Bedford 
2011 BOL ADD BPL10 3334 Crompond Rd. ,Yorktown 
2011 BOL ADD BPL10 Academy Place, Ossining 
2011 BOL ADD BPL10 La Porte, 203 Gramatan Ave.,Mt.Vernon 
2011 BOL ADD BPL10 75 Stratton St. South,Yonkers 
2011 BOL ADD BPL10 50 Warburton Ave.,Yonkers 
2011 BOL ADD BPL10 303-307 S.Broadway,Yonkers 
2011 BOL ADD BPL10 22 Tarrytown Rd.,Tarrytown 
2011 BOL ADD BPL10 500 Main St.,New Rochelle 
2010-50 5/10/2010 BLA01 Memorial Field - Mt. Vernon $9,700,000 
2011 BOL ADD BLA01 Parkland/Legacy Rye Town-A soccer field and girl’s softball field that will be located in Rye Town. $6,000,000 
2011 BOL ADD BPL26 Flood Mitigation $2,500,000 
2011 BOL ADD BLA01 Parkland/Legacy Tibbets Brook-Tibbetts Field Renovations to Northern Miracle Field $2,000,000 
2011 BOL ADD BPL01 Housing Implementation-To restore to annual funding level $2,000,000 
2011 BOL ADD BPL10 New Homes Land Acquisition-To restore to annual funding level $2,000,000 
2011 BOL ADD BLA01 Parkland/Legacy 4th St Playground-Construction Costs $1,250,000 
2011-64 5/23/2011 BPL10 LaPorte $3,710,000 
2012 BOL ADD BLA01 Housing Acquisition Rye Town Legacy Fields (Port Chester) $6,000,000 
2012 BOL ADD BLA01 Parkland Property Acquisition $5,000,000 
2012 BOL ADD BPL01 Housing Implementation $5,000,000 
2012 BOL ADD BPL10 New Homes Land Acquisition $5,000,000 
2012 BOL ADD BPL26 Flood Mitigation $5,000,000 
2012 BOL ADD BPL19 SawMill River Basin Ecosystem restoration $1,232,380 PUBLIC SAFETY - 2 Projects - $1,130,000
RECREATION FACILITIES - 73 Projects - $96,454,000
Status Act # Date Passed Capital Project # Description Bonds Requested 
2013-75 5/6/2013 RNWP1 North White Plains Parking Lot $4,870,000 
2013-58 5/6/2013 RLAS3 Lason Maintenance Facility $3,100,000 
2013-50 4/15/2013 RMUS3 Muscoot Farm Infrastructure-Recreational Area Improvements $100,000 
2013-46 4/15/2013 RGP04 Park Wide Boiler Replacement $350,000 
2013-52 4/15/2013 RGC12 Dunwoodie Golf Course Facility Imporvement $350,000 
2013-53 4/15/2013 RLAS5 Lasdon Park Buildings $370,000 
2011 BOL ADD RKL01 Tarrytown Lighthouse-Restore Project $800,000 
2012-164 11/13/2012 RGIP5 General Infrastructure-Roofing Systems $800,000 
2011 BOL ADD RP044 Playland Pool Infrastructure $750,000 
2011-92 08/08/2011 RML01 Mountain Lakes Park Infrastructure $700,000 
2011-114 08/08/2011 RCC10 County Center Site Work $685,000 
2013-1 01/07/2013 RLAS1 Lasdon Infra/Site Work $670,000 
2008 BOL ADD RM102 Marshlands Site Work $600,000 
2012-47 05/07/2012 RTB05 Tibbets Brook Park Infrasctructure Design $575,000 
2011-69 05/23/2011 RKL01 Tarrytown Lighthouse Restoration $552,000 
2011-94 07/11/2011 RGI11 General Infrastructure: Parks and Bridges $500,000 
2012-109 09/10/2012 RGIP7 General Infrastructure Active Recreation Areas $500,000 
2012-42 04/30/2012 RGC17 Golf Course Fairway Renovation $500,000 
2011 BOL ADD RGC02 Maple Moor Building- Rehabilitation $475,000 
2012-43 04/30/2012 RGC02 Maple Moor Building Rehab $475,000 
2011 BOL ADD RLEN1 Lenoir Preserve- Infrastructure/Site Work $460,000 
2012-46 04/30/2012 RBM04 Blue Mountain Reservation-Building Rehab $460,000 
2011-199 12/12/2011 RWPR1 Ward Pound Ridge Reservation Restoration $450,000 
2009-211 12/07/2009 RMS01 Merestead Site Development $400,000 
2011 BOL ADD RML01 Mountain Lakes Park Infrastructure-Pool Used By N. Salem town Camp $400,000 
2012-41 04/30/2012 RBM05 Blue Mountain Sportsman Center Rehab Ii $400,000 
2011 BOL ADD RGC12 Dunwoodie Golf Course-Facility Improvements $350,000 
2011-198 12/12/2011 RMUS6 Muscoot Building Restoration $350,000 
2009-25 03/05/2009 RP006 Various Rides and Components $345,000 
2012-39 04/16/2012 RGC14 Golf Course Irrigation Rehab $340,000 
2013-5 01/07/2013 RGIP7 General Infrastructure Active Recreation Areas $325,000 
2009-32 03/05/2009 RBR01 Bronx River Parkway Pathways $309,000 
2009-48 03/23/2009 RPA01 Pathways and Trails $300,000 
2011-200 12/12/2011 RWPR3 Ward Pound Ridge Site Work $300,000 
2012-40 04/30/2012 RGC05 Mohansic Golf Course Rehab $300,000 
2012-44 04/30/2012 RGC14 Golf Course Cart Path Rehab Dunwoodie Yonkers $236,000 
2012-163 11/13/2012 RGI12 General Infrastructure-Paving & Resurfacing Ii $210,000 
2009-122 07/07/2009 RP046 Solid Waste Management $125,000 
2008 BOL ADD RBR02 Scout Field $100,000 
2012-45 04/30/2012 RGC18 Scout Field $100,000 
2012 BOL ADD 07/12/2010 B0045 Putnam Right of Way South County Trailway $50,000 
2013-09 01/28/2013 RP009 Playland Ice Casino Storm Repairs $4,925,000 
2013-08 01/28/2013 RP010 Playland Storm Repairs $7,570,000 
2013-14 RTB06 Tibbett's Bathhouse Infrastructure Rehabilitation $450,000 
2013-17 RWPR1 Ward Pound Ridge Historic Bldgs $4,250,000 
2013-18 RWPR3 Ward Pound Ridge Historic Reserve-Site Work $4,075,000 
2011-56 05/23/2011 RPL02 Pocantico Lake Dam Reconstruction $5,980,000 
2010-110; 2010-111 09/07/2010 RTB06 Tibbetts Bathhouse Infrastructure Rehab $5,900,000 
2011-55 05/23/2011 RTL01 Twin Lakes Dam Reconstruction $4,640,000 
2011 BOL ADD NEW Soccer Fields at Bradhurst Avenue $4,000,000 
2011 BOL ADD RMS01 Merestead Site Development-Safety & Code Improvements $3,660,000 
2012-127 09/24/2012 RKD01 Kensico Dam Plaza Infrastructure/site work $3,262,000 
2011 BOL ADD RKL02 Kingsland Bath house-Restore Project $2,800,000 
2012-67 06/18/2012 RGP08 General Infrastructure Vehicle Replacement $2,000,000 
2009-93 06/08/2009 RP042 Playland Site Improvements $1,950,000 
2010-145 11/08/2010 RGIP8 Gen'l Infrastructure-Parks, Bridges, Dams $1,950,000 
2010-70 07/12/2010 RMH01 Miller Farmhouse $1,200,000 
2011 BOL ADD RKP01 Kingsland Point Park- Infrastructure $1,200,000 
2011 BOL ADD NEW Saxon Woods Golf-Water Retention Project $1,200,000 
2012-96 08/06/2012 RGC18 Golf Course General Infrastructure $1,200,000 
2009-58 04/13/2009 RP040 Playland Administration Building Rehabilitation $1,100,000 
2012-95 08/06/2012 RGC20 Golf Course Cart Path Rehab (Sprain Lake) $1,010,000 
2009-89 05/26/2009 RGP08 General Infrastructure: Vehicle Replacement $1,000,000 
2009-56 04/13/2009 RP051 Playland Lighting Replacement $950,000 
2007-192 9/24/2007 RGP04 Park Wide Boiler Replacement $2,150,000 
2011-41 3/28/2011 RGI03 Glen Island Bridge Rehab II $1,200,000 
2007-191 9/24/2007 RGIP8 General Infrastructure Parks Bridges and Culverts $950,000 
2008-148 8/11/2008 RCP7B Croton Point Day Uses & Picnic Areas $400,000 
2008-217 11/24/2008 RGC19 Saxon Woods Golf Course Maintenance $350,000 
2008-28 3/11/2008 RKD01 Kensico Dam Plaza Infrastructure/Site Work $350,000 
2005-214 10/11/2006 RCP10 Croton Point Park Maintenance Facility $300,000 
2008-235 12/8/2008 RGIP8 General Infrastructure Parks Bridges and Culverts $300,000 
2008-149 8/11/2008 RWW02 Willson's Woods Pool Modernization $150,000 REFUSE DISPOSAL - 3 Projects - $11,770,000
Status Act # Date Passed Capital Project # Description Bonds Requested 
2012-171 11/26/2012 RD075 Croton Landfill Stations Pump Station Rehabilitation Program $5,500,000 
2012-170 11/26/2012 RD016 Croton Landfill Rehabilitation and Gas to Energy Program $100,000 
2010-82 7/12/2010 RD004 Sprout Creek Cell Closure $6,170,000 ROADS, BRIDGES & PARKWAYS - 51 Projects - $90,639,000
Status Act # Date Passed Capital Project # Description Bonds Requested 
2013-30 2/25/2013 RB03B Butlerville Road over the Croton River, Somers $320,000 
2013-29 2/25/2013 P0024 Bronx River Parkway Rehabilitation Program (Bronx Line to Scarsdale Road) $820,000 
2013-28 2/25/2013 RB03H Midland Avenue over the Bronx River Parkway $1,680,000 
2013-27 2/25/2013 P0023 Bronx River Parkway Service Bridge $180,000 
2011-116 8/8/2011 RB03E Greenacres Avenue Over BRP $1,370,000 
2012 BOL ADD RB01Q Ashford Avenue Bridge $1,000,000 
2012 BOL ADD RB03L Pondfield Road West Over the BRP $1,000,000 
2009-88 5/26/2009 RB01J Pleasantville Rd Over Pocantico River, Briarcliff Manor $950,000 
2009-113 5/26/2009 RB2VV Bowman Ave Over Blind Brook, Harrison $915,000 
2012-11 3/12/2012 RB2KK Warburton Ave Over Factory Ln, Hasitngs-on-Hudson $9,000,000 
2012-12 3/12/2012 RB2KK Warburton Ave Over Factory Ln, Hasitngs-on-Hudson $900,000 
2012 BOL ADD RB03M Mamaroneck Ave Over Mamaroneck River $800,000 
2012 BOL ADD P0015 Bronx River Restorationriverbank Stabilization $800,000 
2007-103 5/21/2007 P0020 Bronx River Parkway Over Bronx River Yonkers/Eastchester $790,000 
2009-100 6/8/2009 RB119 Bedford/Banksville Road (Greenwich), C.R. 12, Bedford $770,000 
2012-60 6/4/2012 RB127 Fort Hill Rd C.R. 142, Yonkers $705,000 
2008-45 4/7/2008 RB099 Post Rd C.R. 53 White Plains $1,840,000 
2008-49 4/7/2008 RB098 Virginia Rd, North Castle and Mt. Pleasant $600,000 
2011-96 7/11/2011 RB128 Pleasantville Rd and Briarcliff Manor, Mount Pleasant $520,000 
2012 BOL ADD RB03K Access Ramp Smrp North Bound, Dobbs Ferry $500,000 
2012-59 6/4/2012 P0025 BRP Northbound Ramp Over to CCP Westbound Yonkers and Mount Vernon $441,000 
2009-167 8/5/2009 P0022 Northbound BRP Access Ramp @ Elm St, Tuckahoe $310,000 
2006-99 5/22/2006 RB073 Jay Street, Bedford $260,000 
2012 BOL ADD RB03I Tuckahoe Rd Over the BRP $250,000 
2012-83 7/9/2012 RB142 South Street Division Crompound Rd Peekskill $240,000 
2005-98 4/11/2006 RB097 Weaver Sreet, New Rochelle/Scarsdale $120,000 
2012 BOL ADD RB03J Halstead Ave Over Mamaroneck River $100,000 
2012-139 10/15/2012 RB03C June Road Over Titicus River, North Salem $90,000 
2012-66 6/18/2012 RB117 Mill Rd, C.R. 82, Eastchester and New Rochelle $83,000 
2012-81 7/9/2012 RB111 North Division St. C.R.R 63ii Peekskill $35,000 
2013-12 RB03F Ardsley Road Over Bronx River and BRP Scarsdale and Greenburgh $450,000 
2011-47 4/11/2011 P0018 Bronx River Pkway at Crane Rd $8,180,000 
2012 BOL ADD P0024 Bronx River Parkway Rehab Program $8,000,000 
2009-200 11/23/2009 RB2UU Fulton Avenue Bridge over Hutchinson River, Mt. Vernon $6,370,000 
2008-44 4/7/2008 RB03A PALMER RD OVER CENTRAL PARK AVENUE, YONKERS $4,520,000 
2005-146 6/20/2006 RB088 REHABILITATION OF RIDGE STREET AND WAPPANOCCA AVENEUE, RYE/RY BROOK $4,200,000 
2011 BOL ADD RB03F Ardsley Road over BRP-Rehabilitate two bridges at Ardsley Road,
one over the Bronx River and the other over the Bronx River Parkway.$4,045,000 
2009-112 6/22/2009 RB2TT Croton Falls Rd over Croton River, North Salem $3,970,000 
2012-162 11/13/2012 P0022 NorthboundBRP access ramp Elm St, Tuckahoe $2,960,000 
2011-155 10/3/2011 RB110 West and East Main St, C.R. and 25I, Peekskil $2,810,000 
2012-61 6/4/2012 RB03D Palmer rd over Bronx River, Yonkers and Bronxville $2,375,000 
2009-96 6/8/2009 RB102 Palmer Rd & Access Ramps, CR 9, 33II, 33 III, Yonkers $2,350,000 
2012-19 3/26/2012 RB108 North Broadway c.r. 87, wp $2,080,000 
2011-143 10/3/2011 RB121 Broad St Viaduct, CR 132, Yonkers $2,010,000 
2012 BOL ADD P0006 Bronx River Restoration Pond Rehab $1,500,000 
2012-98 8/6/2012 RB03R PIER REHABILITATION ASHFORD AVENUE BRIDGE $1,500,000 
2008-55 4/28/2008 RB072 REPLACEMENT OFF HIGHWAY/ TRAFFIC CONTROL SIGNAGE $1,430,000 
2007-102 5/21/2007 P0019 BRONX RIVER PARKWAY OVER BRONX RIVER YONKERS/EASTCHESTER $1,380,000 
2007-104 5/21/2007 RB01Q ASHFORD AVENUE BRIDGE OVER I-87, ARDSLEY $1,100,000 
2009-201 11/23/2009 P0018 BRP (at Crane Rd) over Bronx River and Rail Road $1,020,000 
2011 BOL ADD RB020 Warburton Ave Hastings-To restore project-On deappropriated list $1,000,000 SEWER & WATER DISTRICTS - 65 Projects - $636,126,400
Status Act # Date Passed Capital Project # Description Bonds Requested 
2013-74 5/6/2013 SW006 Vulnerability Assessment Studies
$ 900,000 
2013-57 5/6/2013 SBB85 Sewer System Rehab-Blind Brook SSD $ 700,000 
2013-56 5/6/2013 SBB30 Blind Brook Wastewater Treatment-Roof Replacement $ 80,000 
2012-180 2012-12-10 SY043 Yonkers Joint WWTP Post Storm Sandy Reconstruction and Rehabilitation
$ 9,950,000 
2012-178 2012-12-10 SW005 Post Storm Sandy Reconstruction and Rehabilitation - Various Sanitary Sewer Districts $ 1,850,000 
2012-179 2012-12-10 SW043 Yonkers Joint WWTP Post Storm Sandy Reconstruction and Rehabilitation $ 9,950,000 
2012-167 2012-11-26 WD001 Eastview Distibution Center $ 2,300,000 
2012-158 2012-11-13 SM085 Sewer System Rehab-Mamaroneck Sanitary Sewer District $ 1,000,000 
2012-132 2012-09-24 SM075 Pumpstation Rehab Program Mamaroneck Ssd $ 8,231,400 
2012-133 2012-09-24 SPK20 Forcemain Rehab Peekskill Sewer District $ 5,700,000 
2012-129 2012-09-24 SPK08 Highland Avenue Pump Station Rehab $ 3,270,000 
2012-55 2012-05-21 SH075 Pump Station Rehab-Hutchinson Sewer District $ 5,700,000 
2011-183 2011-12-22 SY009 Yonkers Joint Treatment Plant-Odor Control and HVAC-Move From Yr. 2013 $ 6,863,000 
2011-149 2011-10-03 SPS05 North Yonkers Pump Station Upgrades (Structural Repairs) $ 1,100,000 
2011-144 2011-10-03 SY030 Yonkers Joint Treatment Plant - Roof Replacement S&G Building $ 650,000 
2011-147 2011-10-03 SPC37 Port Chester Waste Water Treatment Plant Bulkhead Rehab $ 100,000 
2011-148 2011-10-03 SPS37 North Yonkers Pump Station Bulkhead Rehab $ 100,000 
2011-136 2011-09-19 SY037 YJTP Bulkhead Rehabilitation- Phase Ii $ 2,500,000 
2011-137 2011-09-19 SY020 Tarrytown Force Main Replacement $ 2,000,000 
2011-134 2011-09-19 SM075 Pump Station Rehab Program Mamaroneck Ssd $ 1,500,000 
2011-115 2011-08-08 SPK12 Peekskill Wastewater Treatment Plant Sludge $ 2,700,000 
2011-35 2011-03-08 SOS85 Sewer System Rehab- Ossining (Snowden Ave. Odors Remediation) $ 200,000 
2010-131 2010-10-04 SPK14 Heating System Upgrades - Peekskill WWTP $ 1,600,000 
2010-118 2010-09-20 SPC11 Port Chester WWTP - Prim. Settling Tank Bldg. Roof Replacement $ 105,000 
2010-79 2010-07-12 SY085 Sewer System Rehab (Hutch Valley Trunk Reloc. and Cmom Design) $ 2,550,000 
2010-78 2010-07-12 SY085 Sewer System Rehab(N. Yonkers Trunk Emerg. Repair In Hastings) $ 1,250,000 
2009-192 2009-11-09 SPS08 North Yonkers Pump Station - 54" Main Surge Chamber $ 3,500,000 
2009-184 2009-09-09 SSM74 Pump Station Rehab Program-Saw Mill Sanitary Sewer Dist $ 1,100,000 
2009-188 2009-09-09 SY025 Yjtp-Upgrade of Daf & Related Secondary Sludge Equip $ 850,000 
2009-183 2009-09-09 SY018 Yonkers Jtp-Sluice Gate Replacement $ 800,000 
2009-190 2009-09-09 SY017 YJWTP Chloride Contact Tank & Gas Piping Upgrade $ 3,632,000 
2009-189 2009-09-09 SM016 Mamaroneck WWTP-Primary, Secondary Heating & Chem $ 800,000 
2009-194 2009-09-09 SLI03 Long Island Sound Bnr Water Quality Improvements $ 450,000 
2009-162 2009-08-10 SNR75 New Rochelle-Pump Station Rehab Program (Woodbine & Magnolia) $ 5,610,000 
2009-127 2009-08-10 SM003 Mamaroneck WWTP Struct. Rehab of Adm Bldg, Roof Etc $ 2,750,000 
2009-126 2009-08-10 SOS09 Ossining WWTP-Boiler & Generator Replacement $ 1,800,000 
2009-163 2009-08-05 SPS07 Repair & Upgrade of Alexander St Influent Struc & Nyonkers Ps tower $ 2,550,000 
2009-70 2009-04-27 SNR06 New Rochelle-Composite Performance $145,000,000 
2009-26 2009-03-05 SPS02 North Yonkers Pump Station - Upgrading of Pumps $ 3,300,000 
2008-239 2008-12-09 SL101 Long Island Sound Biological Nutrient Removal Remediation $234,700,000 
2008-183 2008-11-24 SOS05 Ossining Waste Water Treatment Plant-Twin Feeder Aerial Cable Replacement $ 600,000 
2008-206 2008-11-10 SY016 Yonkers Joint Treatment Plant Storage Building $ 9,900,000 
2008-189 2008-10-20 SY009 Yonkers Joint Treatment Plant Odor Control and HVAC Upgrades $ 9,635,000 
2008-195 2008-10-20 SY42B Yonkers Joint Treatment Plant Odor Control, Additional Mitigation $ 3,200,000 
2008-142 2008-08-11 SM007 Mamaroneck Wastewater Treatment Plant Performance Maintenance $ 3,750,000 
2008-139 2008-08-11 SBB30 Sewer System Rehabilitation $ 300,000 
2008-138 2008-08-11 SPK85 Sewer Rehabilitation - Peekskill Sanitary Sewer District $ 200,000 
2008-41 2008-04-07 SY021 Yonkers Joint Treatment Plant Dewatering Equipment $ 3,650,000 
2008-05 2008-02-11 SPC09 Port Chester Waste Water Treatment Plant HVAC Systems Upgrade $ 200,000 
2007-223 2007-10-22 SBB06 Blind Brook Wastewater Treatment Plant Performance Maintenance $ 9,000,000 
2007-124 2007-06-18 SY085 Sewer System Rehabilitation - Yonkers Jt. Plant Districts $ 3,450,000 
2007-84 2007-04-26 SPC37 Port Chester Waste Water Treatment Plant - Bulkhead Rehabilitation $ 2,200,000 
2007-86 2007-04-23 SPS04 North Yonkers Pump Station Electrical Equipment Upgrade $ 8,000,000 
2007-87 2007-04-23 SPS05 North Yonkers Pump Station Upgrades $ 5,000,000 
2007-68 2007-03-26 SY006 Yonkers Joint Treatment Plant - Automatic Skimming System $ 4,500,000 
2007-03 2007-01-22 SW020 Forcemain Replacement - Various Districts $ 200,000 
2005-235 2006-11-15 SW020 Forcemain Replacement - Various Districts $ 200,000 
2006-178 2006-09-25 SY027 Yonkers Joint Treatment Plantprimary Sludge Divesters Roof Replacement $ 4,750,000 
2006-176 2006-09-25 WD177 Water District No. 1 Security Projects $ 1,000,000 
2005-147 2006-06-06 SNR20 Mamaroneck/Newrochelle Twin Sludge Forcemain $ 6,000,000 
2012 BOL ADD NEW Water District #1 Facilities for Provision of Ultraviolet $ 50,000,000 
2001-32 SNR85 Sewer System Rehabilitation New Rochelle Sanitary Sewer District $ 23,300,000 
2011 BOL ADD NEW Sanitary Sewer Collection-Sanitary Sewer Collection System/Direct to County Treament Facility $ 6,800,000 
2001-88 SW004 Sewer Districts Facility Plans $ 400,000 
2003-103 SW020 Forcemain Replacement - Various Districts $ 200,000 SOCIAL SERVICES - 5 Projects - $6,171,000
Status Act # Date Passed Capital Project # Description Bonds Requested 
2007-199 2007-10-09 BSS11 New Yonkers District Offfice at I-Park, Warburton Avenue, Yonkers $4,231,000 
2009-123 2009-07-07 BSS12 Infrastructure Improvements to Shelter Facilities (2009-2013) $ 860,000 
2005-188 2005-09-12 BSS10 Infrastructure Imporvements to Shelter Facilities $ 500,000 
2006-126 2006-06-19 BSS10 Infrastructure Imporvements to Shelter Facilities $ 500,000 
2012-84 2012-07-09 BSS13 Infrastructure Imporvements to Shelter Facilitites, Mt Vernon $ 80,000 TRANSPORTATION - 4 Projects - $4,279,062
Status Act # Date Passed Capital Project # Description Bonds Requested 
2011-128 2011-09-06 T001N Transit Bus Replacement $2,644,793 
2009-166 2009-08-05 T0033 Bus Wash - Centralized Maintenance $ 800,000 
2011-130 2011-09-06 T001T Articulated Bus Rehabilitation $ 656,144 
2011-123 2011-09-06 T0034 Maintenance Facilities Infrastructure $ 178,125 WESTCHESTER COMMUNITY COLLEGE - 19 Projects - $51,888,500
Status Act # Date Passed Capital Project # Description Bonds Requested 
2011-145 10/3/2011 WCC63 Site Improvements - Parking, Walkways & Kiosks $1,384,000 
2011-146 10/3/2011 WCC67 Health Sciences Building Renovations/Improvements $1,181,000 
2011-141 9/19/2011 WCC65 Electrical/Mechanical Upgrades Various Buildings $2,022,000 
2011-139 9/19/2011 WCC70 Physical Education Building Renovations/Improvements $2,098,000 
2011-140 9/19/2011 WCC78 Safety and Security Improvements $2,045,000 
2010-130 10/4/2010 WCC56 Physical Education Field Improvements $1,433,000 
2010-134 10/4/2010 WCC57 Utility Drainage Infrastructure Upgrade $539,500 
2010-135 10/4/2010 WCC68 Administration Building Renovations $1,384,000 
2010-136 10/4/2010 WCC70 Physical Education Building Renovations/Improvements $181,000 
2010-108 9/7/2010 WCC20 Student Center Improvements $9,900,000 
2010-109 9/7/2010 WCC78 Safety and Security Improvements $1,146,000 
2008-106 7/8/2008 WCC43 Technical Building Renovations/Improvements $7,048,000 
2008-105 7/8/2008 WCC44 Classroom Building Renovation Improvements $1,590,000 
2008-99 7/8/2008 WCC45 Academic Arts Building Renovation Improvements $2,039,000 
2008-102 7/8/2008 WCC52 Campus Wide Traffic Site Project $700,000 
2008-107 7/8/2008 WCC66 Science Building Renovation Improvements $3,689,000 
2008-104 7/8/2008 WCC69 Hartfold Hall Renovation Improvements $1,109,000 
2007-70 3/26/2007 WCC53 Gateway Building $9,900,000 
2007-71 3/26/2007 WCC54 Furniture and Equipment For Gateway Center $2,500,000